9/22/23 Kentwood Residents:
See below for schedule. For portions of the day, access to your street will be limited. Please talk with our on site traffic personnel
See below for schedule. For portions of the day, access to your street will be limited. Please talk with our on site traffic personnel
The final part of the cape sealing process will occur Thurs 9/21. For portions of the day, access to your street will be limited.
The second & final part of the cape sealing process will occur Wed. 9/20. For portions of the day, access to your street will
Your streets will be Micro Surfaced this Wednesday and Thursday, 9/13 & 9/14. Please park in your driveway or an unaffected street. There will
The microsurfacing part of the process is scheduled to start today, Sunday, and go into Monday next week. For short periods of the day,
Your streets will be chip sealed next Tuesday, 9/12. Please park in your driveway, you’ll be able to get in and out with no
Your streets will continue to be chip sealed Sunday. Please park in your driveway, you’ll be able to get in and out with no
Spring Lake Township: Tomorrow 9/6 will feature the first portion of the cape seal process. Please park in your driveway, access will be unaffected.
Due to mechanical issues the past several days, we’ve elected to take tomorrow to fix our equipment. There will be no resurfacing taking place
Day 4 of your road surfacing project has been pushed to Thursday 9/7 instead of Wednesday, due to trash pickup. See map below. #SCIResidentUpdates
Our chip sealing schedule is below. Please park in your driveway. Access will be unaffected. #SCIResidentUpdates
This week’s Micro Surfacing schedule is below. Please call Andrew Friend @ 614-824-8782 with access issues. Thanks for your patience. #SCIResidentUpdates
No work is scheduled to begin in Kentwood until Tuesday, 8/29. Access to your home will be unaffected all week. Just please park in
Due to last night’s storms, all paving has been postponed until Monday/Tuesday next week in residential areas. #SCIResidentUpdates
Next Monday and Tuesday, 8/28 and 8/29, repairs will be taking place. Most of these repairs are in the cul-de-sacs. If your cul-de-sac is
Due to weather, your road resurfacing project is delayed until next Wednesday, 8/30. See updated schedule below #SCIResidentUpdates
Westerville Residents: Your roads are scheduled for resurfacing starting tomorrow, 8/25, with Day 1 (weather permitting). Road list attached plus maps for Day 1
On Wednesday, 8/23, the first portion of cape sealing will take place on the streets listed below. Please park in your driveway. Access in
Our schedule for the remainder of your streets is below. Please call Andrew Friend at 614-824-8782 with any questions or concerns. Thanks for your
Your road resurfacing project starts tomorrow, 8/15, as Day 1, weather permitting. See attached maps. Day 2 = 8/16, Day 3 = 8/17, weather permitting. Check back for updates #SCIResidentUpdates
Our paving schedule for next week is below. In lieu of Monday’s weather forecast, we’re going to resume paving on Tuesday, 8/15. #SCIResidentUpdates
Construction is on hold until next Monday, 8/14. We will post an updated schedule on our website Friday morning. Thank you. #SCIResidentUpdates
Today’s schedule is below. Please call Andrew Friend @ 614-824-8782 to see if your street is ready to drive on. Residents in the northern
Due to primary elections, Wetherfield and Sturbridge have been pushed to Wednesday, 8/9. Instead, we will be doing Finley Lane, Lyncris and Sandymar. Residents
We promise to listen to everything you want and deliver everything you need for safer, more durable roadways—today and in the future.